I learned PSSU(Power System Simulator for Utilization) and PSS/Adept(Advanced Distribution Engineering Productivity Tool) which used to model,simulate and analyse network in a distribution system.
I was given assessment of Pulau Pangkor Sytem Diagram .Important data such as node,voltage(kv),static load(kva,pf),input data(from-to),lenght(km) and size needed in order to get the output.I tried for few times because there is an error showing as red line in network.Finally i realised that i wrongly read the value of kva and pf instead of kw and kvar.
I also suggested the best off-point in the network during breakdown .In the power company's (or its customer's),best interest that major loads on the system have pf~1.It is also beneficial to install capacitors to improve the pf(power factor).